1. Ready

A feature may enter development only when the following conditions are met:

  • API Contract is reviewed and approved

  • Postman Collection is prepared

  • Test Cases are reviewed and approved

  • Backend and Frontend tasks are created and clearly defined on the board


2. In Development

  • Backend and Frontend subtasks are created under the same Feature

  • Development work follows defined WIP limits

  • WIP Limit based on the number of Developers


3. Code Review

All development work must pass through Code Review:

  • Pull Request (PR) must be created

  • Reviewer assignment is mandatory

  • WIP Limit for Code Review column = 6

  • PR must be approved before merging


4. Dev Deployment

A task is considered Dev Deployed only when:

  • PR is approved

  • Merge is completed

  • Build succeeds

  • Deployment pipeline succeeds on Dev environment


5. Backend Ready for Testing

Entry Criteria:

  • Backend is successfully deployed on Dev

  • API endpoints are available and accessible

The tester begins API validation using Postman.


6. Backend Tested

The backend is considered tested only when:

  • API is validated against the approved contract

  • No breaking changes were introduced without contract approval

  • No Critical bugs exist

  • Happy Path scenario is fully functional


7. Ready for Integration

Entry Criteria:

  • Backend is fully tested

  • Frontend is deployed on Dev

The feature is now eligible for integration.


8. Ready for End-to-End (E2E) Testing

  • Integration between Backend and Frontend is completed

  • Latest Dev deployment includes both components

The tester begins full feature validation.


9. Done

A feature is considered Done to be moved to stage only when:

  • API Testing is completed

  • End-to-End Testing is completed

  • No open Critical or blocking bugs exist

  • The feature is stable on the Dev environment


Governance Rule

A feature cannot move to the next stage unless all entry conditions of the current stage are satisfied.